Thursday, 5 December 2024
Home Topics Transport Electric Vehicles (EVs) Vibrations in cooling system mean new Georgia nuclear reactor will again be delayed
Electric Vehicles (EVs)ElectricityNewsNuclear Power

Vibrations in cooling system mean new Georgia nuclear reactor will again be delayed

71
Units 3, from left, and 4 are pictured at Plant Vogtle near Waynesboro, Ga., on Monday, July 31, 2023. Georgia Power Co. announced on Thursday, Feb. 1, 2024, that commercial operation of Unit 4 will be delayed into 2024's second quarter after the company detected and fixed a vibration problem in the reactor's cooling system. Photo: Arvin Temkar/Atlanta Journal-Constitution via AP/file

ATLANTA (AP) — Georgia Power Co. said Thursday that vibrations found in a cooling system of its second new nuclear reactor will delay when the unit begins generating power.

Plant Vogtle’s Unit 4 now will not start commercial operation until sometime in the second quarter of 2024, or between April 1 and June 30, the largest subsidiary of Atlanta-based Southern Co. announced.

The utility said in a filing to investors that the vibrations “were similar in nature” to those experienced during startup testing for Unit 3, which began commercial operations last summer, joining two older reactors that have stood on the site near Augusta for decades

In that case, the utility found that a pipe vibrated during testing because construction workers hadn’t installed enough bracing. Georgia Power said the Unit 4 problem has already been fixed but too much testing remains to be done to make the March 30 deadline.

Georgia Power said it’s likely to lose $30 million in profit for each month beyond March that Unit 4 isn’t running because of an earlier order by state utility regulators. The five members of the Georgia Public Service Commission ordered that the company can’t earn an additional return on equity through a construction surcharge levied on Georgia Power’s 2.7 million customers after March 30.

The typical residential customer has paid about $1,000 in surcharges over time to pay for financing costs.

The company said its construction budget won’t be affected if Unit 4 starts by June 30 but it would have to pay $15 million a month in extra construction costs if the project extends into July.

Regulators in December approved an additional 6% rate increase to pay for $7.56 billion in remaining costs at Vogtle, expected to cost the typical residential customer $8.95 a month. That’s on top of the $5.42 increase that took effect when Unit 3 began operating.

The new Vogtle reactors are currently projected to cost Georgia Power and three other owners $31 billion, according to calulations by The Associated Press. Add in $3.7 billion that original contractor Westinghouse paid Vogtle owners to walk away from construction, and the total nears $35 billion.

The reactors were originally projected to cost $14 billion and be completed by 2017.

Units 3 and 4 are the first new American reactors built from scratch in decades. Each can power 500,000 homes and businesses without releasing any carbon. But even as government officials and some utilities are again looking to nuclear power to alleviate climate change, the cost of Vogtle could discourage utilities from pursuing nuclear power.

Georgia Power owns 45.7% of the reactors, with smaller shares owned by Oglethorpe Power Corp., which provides electricity to member-owned cooperatives; the Municipal Electric Authority of Georgia; and the city of Dalton.

Some Florida and Alabama utilities have also contracted to buy Vogtle’s power.

Jeff Amy, The Associated Press

Related Articles

FILE PHOTO: Tesla electric vehicles use a Tesla supercharging station in Union City, New Jersey, U.S., July 23, 2024.  REUTERS/Eduardo Munoz/File Photo
AutomotiveElectric Vehicles (EVs)Transport

EVs, plug-in hybrids’ reliability concerns ease but still lag gas-powered peers, survey shows

EVs now have 42% more problems than their gas-powered counterparts, down from...

Drought has emptied the  Jablanicko artificial lake in Bosnia that was once a major tourist attraction for the town of Konjic (AFP)
ClimateElectricityEnvironmentHydropowerWeather

‘Scary’ drought empties one of Bosnia’s largest lakes

"The year 2024 was exceptionally bad for the functioning of the power...

Sir Keir Starmer set out his Government’s ‘plan for change’ at Pinewood Studios in Slough on Thursday (Darren Staples/PA)
ElectricityFuelNatural GasSolarWind

Starmer denies watering down green power target in new ‘plan for change’

The Labour election manifesto promised “zero-carbon electricity” — but critics say the...

Intense flooding in Europe alone caused around $10 billion in insured losses this year, Swiss Re said (AFP)
ClimateEmissionsResiliencyWeather

Natural disasters cause $310bn in economic losses in 2024: Swiss Re

It marks the fifth consecutive year that insured losses have topped $100...

Login into your Account

Please login to like, dislike or bookmark this article.