With completion in sight, what’s next for the Trans Mountain pipeline project?

39

Workers lay pipe during construction of the Trans Mountain pipeline expansion on farmland, in Abbotsford, B.C., on Wednesday, May 3, 2023. After more than four years of construction and at least $34 billion in costs, the Trans Mountain pipeline expansion project is nearly complete. THE CANADIAN PRESS/Darryl Dyck

CALGARY — After more than four years of construction and at least $34 billion in costs, the Trans Mountain pipeline expansion project is nearly complete. Here’s a look at what milestones to expect in the coming weeks as the massive pipeline gets ready to start shipping Canadian oil to the West Coast:

Resolution of B.C. construction challenges

Crown corporation Trans Mountain Corp. has been dealing with construction-related challenges in the Fraser Valley between Hope and Chilliwack, where it encountered an “obstruction” when trying to pull the pipe into the horizontal hole that had been drilled for it. The setback forced the company to remove the pipe temporarily to address the issue, but Trans Mountain Corp. says it is nearing a resolution and expects to be able to re-install the pipe in that section within the next couple of weeks.

Organizations
Mechanical completion

This marks the final stage of physical construction of the pipeline. Once the challenging segment of pipe has been successfully pulled back into its location, Trans Mountain will be able to complete the “final weld,” or what is formally known as mechanical completion.

Leave To Open

After construction is finished but before the pipeline can be put into service, there are several regulatory steps that must be completed. In accordance with the Canada Energy Regulator Act, companies require permission from the CER before commencing operations of a pipeline. This process is called Leave to Open and requires results from a series of inspections and safety tests. Because the Trans Mountain project has been constructed in phases, the company has been applying for Leave to Open permission in stages in order to allow flexibility during the commissioning and startup process.

Line fill

This term is used to describe the final stages of work required to prepare and ultimately fill the expanded pipeline system with more than four million barrels of oil. The process will take several weeks to complete. While line fill has not yet started on the newly constructed pipe, part of the Trans Mountain expansion project involves reactivating two older pipeline segments that had been maintained in a deactivated state. Initial line fill has already begun in B.C. on that section of the project.

In-service

This term refers to when the entire expanded pipeline system is fully operational and ready to make regular deliveries. According to a Bloomberg report, China’s Sinochem Group has purchased one of the first shipments, a 550,000-barrel cargo from Suncor Energy Inc., which will load from the Trans Mountain expansion pipeline in May-June. Trans Mountain is continuing to target an in-service date sometime in the second quarter of 2024.

Cleanup and reclamation

Once the expanded pipeline is operational, required cleanup and reclamation work will continue in the project’s construction zone.

This report by The Canadian Press was first published March 26, 2024.

The Canadian Press

Note to readers: This is a corrected story. In a previous version, The Canadian Press erroneously reported the expanded pipeline system would eventually be filled with more than four billion barrels of oil. In fact, the pipeline will be filled with more than four million barrels of oil.

Related Articles

FILE PHOTO: Tanker trucks are seen among oil tankers docked at the port of Tuxpan, in Veracruz state, Mexico April 22, 2020. REUTERS/Oscar Martinez/File Photo
AnalysisBusinessFinanceFuelIn-DepthOil

Global refiners face profit slump as new plants come online

Oil refiners in Asia, Europe and the United States are facing a...

FILE PHOTO: Nippon Steel logo is displayed at the company's headquarters in Tokyo, Japan April 1, 2024.  REUTERS/Issei Kato/File photo
BusinessFinanceIndustryManufacturing

Nippon Steel to sell $211 million in assets to manage debt

Nippon Steel agreed with three Japanese banks for $16bn in loans to...

Netley Creek and The Red River enter Lake Winnipeg just north of Winnipeg, Sunday, May 15, 2022. A Manitoba court is being asked to declare Lake Winnipeg a person with Constitutional rights to life, liberty and security of person. THE CANADIAN PRESS/John Woods/POOL
BiodiversityCourtsEnvironmentIndigenousLegislationRegulationsResiliency

‘She is dying’: Lawsuit asks Lake Winnipeg to be legally defined as a person

A lawsuit seeks to grant Lake Winnipeg constitutional rights, pushing for environmental...

FILE - This photo provided by the Center for Biological Diversity shows a Tiehm's buckwheat plant near the site of a proposed lithium mine in Nevada, May 22, 2020. (Patrick Donnelly/Center for Biological Diversity via AP, File)
BiodiversityCritical MineralsElectric VehiclesEnvironmentMiningRegulations

US agency review says Nevada lithium mine can co-exist with endangered flower

U.S. completes review of Nevada lithium mine, says project will supply critical...

Login into your Account

Please login to like, dislike or bookmark this article.