Ottawa negotiates $500 million bailout to prevent electricity rate hike in Nova Scotia

11
Ottawa is negotiating a bailout of $500 million to help avoid a jolting power hike in Nova Scotia related to delivery delays of Muskrat Falls hydroelectricity over the past five years. Environment Minister Jonathan Wilkinson speaks during a press conference in Halifax, Monday, Sept. 16, 2024. THE CANADIAN PRESS/Michael Tu
Environment Minister Jonathan Wilkinson speaks during a press conference in Halifax, Monday, Sept. 16, 2024. — THE CANADIAN PRESS/Michael Tu

HALIFAX — Ottawa is negotiating a $500-million bailout for Nova Scotia’s privately owned electric utility, saying the money will be used to prevent a big spike in electricity rates.

Federal Natural Resources Minister Jonathan Wilkinson made the announcement Monday in Halifax, saying Nova Scotia Power Inc. needs the money to cover higher costs resulting from the delayed delivery of electricity from the Muskrat Falls hydroelectric plant in Labrador.

Wilkinson said that without the money, the subsidiary of Halifax-based Emera Inc. would have increased rates by up to 19 per cent over a few years.

“Nova Scotians already pay higher energy bills than many provinces in the country. Immediate cost recovery of these costs in 2025 could have resulted in a potential near-term increase” in power rates, the minister said during a news conference.

“The action we are announcing today is anticipated to reduce the annual increase very, very significantly.”

The Nova Scotia utility helped pay for construction of the underwater transmission link between Nova Scotia and Newfoundland that carries electricity generated by the Muskrat Falls hydroelectric project in central Labrador.

But the massive dam and generating station has been inconsistent in delivering electricity over the past five years.

While the 180-kilometre undersea link — known as the Maritime Link — was completed on time and on budget, Muskrat Falls has suffered through power production difficulties and software glitches within the Labrador-to-Newfoundland transmission system.

As a result, Nova Scotia homeowners and businesses didn’t receive all of the expected hydro power they expected, and Nova Scotia Power was forced to purchase more expensive and polluting fuels to boost production from their existing generating stations.

Nova Scotia Power CEO Peter Gregg said the deal, once approved by the province’s energy regulator, will keep rate increases limited “to be around the rate of inflation,” as the higher fuel costs are spread over a number of years.

In 2021, Ottawa restructured its financial assistance for the Muskrat Falls project and Newfoundland’s power company to avoid a forecast 75 per cent increase to Newfoundland and Labrador’s power rates. By then, the project’s initial, projected cost in 2012 of $7.4 billion had almost doubled.

Its mounting costs prompted a $5.2-billion bailout from Ottawa.

In December 2023, Nova Scotia’s Progressive Conservative government asked for Ottawa’s help with the potential higher costs resulting from Muskrat Falls.

Wilkinson said the federal Liberals were pleased they could make a deal, saying it’s essential provinces without access to hydroelectricity find green sources of power. He said without this power, companies may move elsewhere to obtain electricity that doesn’t generate carbon emissions.

The announcement Monday comes in the wake of Wilkinson visiting the province in July to announce $192 million in funding for six clean electrical energy projects. That announcement was for three 50-megawatt battery storage systems to be operated by the utility and for three wind farm projects.

Despite the steady flow of money to Nova Scotia in recent weeks, on the weekend Premier Tim Houston repeated his government’s calls for Ottawa to foot the entire bill to protect the Chignecto Isthmus — a vital strip of land connecting the province to New Brunswick — from climate-change related storms.

Kody Blois, the leader of the federal Liberal Atlantic caucus, said he finds it difficult to understand why Houston is taking an antagonistic approach.

“I look at the Facebook page of the premier and it’s almost every other day he wants to create a fight with the government of Canada,” Blois, a Nova Scotia MP, said during Monday’s news conference.

“That’s fine. There’s always going to be times we disagree … but I just hope the premier will recognize the significant contribution this (Liberal) government has made in the province of Nova Scotia.”

Sean Fraser, the federal minister of infrastructure, said the roughly $325 million Ottawa has approved for improving the dikes that protect the Isthmus is the largest amount approved to date under the federal Disaster and Mitigation Adaptation Fund.

He questioned the decision by Nova Scotia and New Brunswick to continue a court battle to have Ottawa shoulder all of the costs, saying the legal fees would be better spent on the project itself.

This report by The Canadian Press was first published Sept. 16, 2024.

Michael Tutton, The Canadian Press

Related Articles

In the absence of public communication from the Pathways Alliance, a clean energy think-tank says the oilsands industry group is running out of time to deliver on its emissions reduction promises. An oilsands facility is reflected in a tailings pond near Fort McMurray, Alta., on July 10, 2012. THE CANADIAN PRESS/Jeff McIntosh
BusinessCarbon ManagementClimateEmissionsLegislationPoliticsRegulations

Pressure still on oilsands sector despite silence after greenwashing law: think tank

Proposed Pathways Alliance carbon capture project should still go ahead, say researchers,...

FILE PHOTO: A worker wearing a face mask works on a production line manufacturing bicycle steel rim at a factory, in Hangzhou, Zhejiang province, China March 2, 2020. China Daily via REUTERS/File Photo
AviationBusinessEconomyEmissionsFinanceIndustryManufacturingMaritime

Weak demand for low-carbon products hampers green investment, COP28 initiative says

Global green investment is lagging behind required levels to help transition heavy...

Quebec Minister of Natural Resources and Forests Maïte Blanchette Vezina tables a legislation on mining May 28 at the legislature in Quebec City.This week, Quebec announced it will not be funding a mining project to produce graphite — one of the world's most sought after minerals. THE CANADIAN PRESS/Jacques Boiss
BusinessCritical MineralsLegislationMineralsMiningPolitics

Quebec won’t fund graphite mine project tied to Pentagon; locals claim ‘victory’

Provincial government rejects company's proposal for graphite mine after residents raise concerns...

FILE PHOTO: Energy supply workers restore a high-voltage line destroyed in Russian missile attack, amid Russia's attack on Ukraine, in Kyiv, Ukraine February 7, 2024. REUTERS/Anna Voitenko/File Photo
ElectricityInfrastructurePoliticsUnited Nations

Russian attacks on Ukraine power grid probably violate humanitarian law, says UN

Monitoring unit reports that campaign against Ukrainian energy infrastructure breach foundational principles...

Login into your Account

Please login to like, dislike or bookmark this article.