Sunday, 19 January 2025
Home Topics Electricity Inter-array cable works completed on Dogger Bank A

The following content is a news release issued by . The original news release may be found here.

Inter-array cable works completed on Dogger Bank A

Over 200 miles/328km of 66KV cables manufactured by Hellenic Cables under a contract with DEME Offshore

23rd July 2024

More than 200 miles (328 km) of 66KV inter-array cables have been successfully installed by delivery partners working on the construction of the world’s largest offshore wind farm.

Organizations
Topics
Projects

The cables were laid by DEME Offshore’s Viking Neptun, with burial works being completed by DEME Offshore’s Living Stone.

This work marks the completion of all inter-array cables on the first phase of the wind farm, Dogger Bank A, which began generating power in October 2023.

The network of 95 cables in a multitude of lengths up to 8.6 miles, will connect Dogger Bank A’s 95 Haliade-X 13MW turbines to the Dogger Bank A offshore convertor station. From here the electricity is converted into direct current for transmission to Dogger Bank A’s onshore convertor station via a pioneering HVDC system.

The laying of cables is carried out using a specialist cable lay vessel that uses a carousel and tensioner device, to deploy cable over the stern chute of the vessel and onto the surface of the seabed. The second stage involves connecting the cable to the offshore platform as well as each individual wind turbine.

This challenging engineering process follows on from an intensive preparation period involving underwater surveys, to ensure the cable laying corridor is clear of obstacles.

The 66KV inter-array cables were manufactured by Hellenic Cables under a contract with Dogger Bank tier one contractor DEME Offshore.

Hellenic Cables and Deme Offshore are also responsible for the manufacture and installation of inter-array cables for Dogger Bank B and C. The first inter-array cable for Dogger Bank B is expected to be installed from autumn 2024.

Alan Evans, Dogger Bank Wind Farm Marine Package Manager, said: 

“This is another important part of our Dogger Bank A marine work complete, and is the result of a great collaboration between all parties involved.

“With 277 cables to be installed in total, it’s by far the biggest inter-array cable installation programme undertaken to date in offshore wind.

“The safe and smooth completion of this phase is a huge credit to the entire team.” 

Geert Linthout, Project Director – DEME offshore, said: 

“The teams at Dogger Bank and DEME Offshore have collaborated closely to achieve this significant project milestone. 

“Throughout the execution, DEME Offshore has successfully deployed both the Living Stone and the newly added cable installation vessel Viking Neptun, demonstrating outstanding performance. 

“This has provided a solid and reliable basis for the upcoming Dogger Bank B phase and, subsequently, the Dogger Bank C phase. We are excited to continue our strong working relationship on Dogger Bank B and Dogger Bank C.”...

Read the full news release here

Related Articles

Flames and smoke from a fire fill the sky at the Moss Landing Power Plant Thursday Jan. 16, 2025 in Moss Landing, Calif. (Shmuel Thaler /The Santa Cruz Sentinel via AP)
Electric Vehicles (EVs)ElectricityEnvironmentSolarWind

A battery plant fire in California started during a boom for energy storage

A major California battery plant fire burned thousands of lithium batteries, a...

FILE PHOTO: Miniatures of windmill, solar panel and electric pole are seen in front of words Clean energy in this illustration taken January 17, 2023. REUTERS/Dado Ruvic/Illustration/File Photo
ElectricityFinanceFuelPolitics

US clean energy tax subsidies to cost $825 billion over 10 years, CBO says

U.S. clean energy subsidies under Biden's Inflation Reduction Act to raise deficits...

Turbines of the WindFloat Atlantic Project, a floating offshore wind-power generating platform, are seen 20 kilometers off the coast in Viana do Castelo, Portugal, September 23, 2021. REUTERS/Violeta Santos Moura/ File Photo
BusinessInfrastructureOffshore WindWind

Portugal keen to create offshore wind cluster, could reach 10 gigawatts

Portugal advances offshore wind plans with a 10 GW goal, approving four...

FILE PHOTO: Solar panels are set up in the solar farm at the University of California, Merced, in Merced, California, U.S. August 17, 2022. REUTERS/Nathan Frandino/File Photo
ElectricityFinanceFuelRegulations

Biden protects 84% of IRA clean energy grants from being clawed back

Biden secures 84 per cent of $96.7B in clean energy grants under...

Login into your Account

Please login to like, dislike or bookmark this article.